Work continued on stripping both 1630 and 1632 North Gilmor homes down to the bare bones. Stairs were removed from 1630 and all unnecessary framing was removed from both houses. The task of removing the old subfloor was also started in both homes, and a temporary support wall was built to support the roof structure along the wall shared between the houses.

Here the crew removed some framing:


A view of top floor of 1632 after removing the framing and subfloor.


The crew works to remove the stairs from 1632:


A temporary support wall under construction:

A little artistic view through the floor joists of 1630.