Thursday, July 8, 2010

Summer Build Week - Part Two

Despite the increasing heat as the week continued on so did progress. Wednesday we had a small crew come out but were joined by our homeowner and her family, and a few other independent volunteers. The day started of with a bit of re-work but we were able to make significant progress in laying down the sub floor on the third level. After a short post lunch hiatus due to a lack of generator fuel, we were able to get most of the framing re-work completed.

Wednesday's Crew




Thursday we had a huge crew including a dozen Northrop folks plus a group from Erickson's IT department joined in. We were able to complete the second floor exterior walls and finish laying all of the sub floor on the third floor. A team started constructing the third floor walls.



We were also able to get the stairwell on the second floor framed in, helping to eliminate the un-obstructed three story drop.



Thursday's Team



Friday we had another good turnout of Northrop folks. Picture taking was kept at a minimum, but framing progressed well. We started to frame and sheath the back walls on the third floor including working the logistics of moving the required plywood and gypsum sheathing to the third floor. A landing was built between the second and third floors which will ultimately accept a set of switchback stairs. A brave crew was able to cut back the roofs on the adjacent houses allowing our house to have a higher roof line to meet an 8 foot ceiling height throughout the third floor.

Friday's Group

Wednesday, June 23, 2010

Summer Build Week underway.

Monday June 21rst and Tuesday June 22nd was the kickoff of Summer Build Week, an annual event at Sandtown where hundreds of volunteers show up during the week to work on 20+ houses, landscaping, and to see and feel the work being done in the community. This year marked the 19th year that Sandtown held the event, but the first year where Northrop Grumman had a significant presence. This year also was poignant due to the recent passing of Allen Tibels who founded the Sandtown Habitat Affiliate.
May we remember Allen, his vision, and his ability to get all people to believe in building Sandtown as a community, not just a bunch of restored houses.


After starting the morning with announcements, many thanks to all the sponsors, churches, homeowners, schools, and groups that volunteered for the day and singing a few songs, we headed to the house. On Monday, we had group of about 12 Northrop folk that showed up and Tuesday we had a mix of three Northrop people and a few friends from Stanley Black and Decker and the US Coast Guard. In that time we made a lot of progress on getting the second and third floor ready. We framed the exterior walls on the second floor and the homeowner and her family exposed the brick wall in the front foyer. We also got all of the joists laid for the third floor and began laying subfloor down on the third floor. All this occurred in the 90+ degree heat. Thankfully the Build Week support group did very well to make sure we had lots of cool liquids available, as well as slices of fruit. Our lunch break was also nice to cool down in the shade and to sit and meet other volunteers from various locations around Maryland and even New York City.

Here are just a few pics I took at the end of the day Tuesday. In the first one you can see us packing up the tools and power cords for the day, and well as the rear of the house where the new second floor windows and framing and the third floor joists are visible. In the second is the view from the second floor.



Many thanks to everyone that came out Monday and Tuesday, and I hope that the 19th Annual Summer Build Week continues to be safe and productive.

-Rob

Thursday, May 20, 2010

May 15, 2010

Another wonderful Saturday work day. This week we had a fairly small group, however were able to enjoy the company of several people who had not been out before as well as several we had not seen in a while. We were also joined once again by Tonya, our homeowner.



We started the day by moving a fresh load of material into the house that was dumped in the alley earlier in the morning. 100+ 2x4s and 25+ sheets of plywood. Figured it was best to take care of this while everyone was still fully charged rather than after everyone was beat and the crew started to 'dissipate'.

In picking up where the Manufacturing group left off, we had several additional I-joists to install on the second floor. In addition there were more squash blocks and rim joists to install before we were ready to lay the subfloor.



The task of framing out the fist floor bathroom was also completed including the stairwell framing for the stairs up to the second floor.



Despite several of us being covered in glue by the end of the day, we were able to lay all of the subfloor on the second level and get a protective coat of shellac to protect our work from the weather. We also started to sheath the back framed section of the house to start being able to close up and secure the house at the end of the day.



We are taking the next 2 week cycle Saturday (the 29th) off for Habitat's observation of Memorial Day, but are looking forward the 12 of June as well as Summer Build Week June 21 through 25.

May 14, 2010

We would like to extend a special thanks to the Manufacturing / Operations group who held a team building event on May 14. This group really found their rhythm and made amazing progress.

When the group arrived they were greeted with a clear first floor deck, and when they left the house was almost ready for the second floor deck installation. Walls were constructed down both sides of the house and most of the second floor I-joists we placed.



Additionally the basement stair well was framed in allowing for the 1st floor half bath floor to be installed.



The Manufacturing / Operations Team

Friday, May 7, 2010

May 1, 2010

Our workday was a gorgeous sunny day which is fairly normal for May. But, what was not so normal was the 90 degree thermometer making our workday feel more like July than May. Despite the heat and sun, though, we had a great turnout and accomplished a lot. Our big focus was to continue working on the first floor's subfloor. Most of the joists had been laid during the last workday, so all we had to do was glue and nail sheets of 3/4" subfloor plywood onto the joists. Seems easy enough but execution can be difficult since the plywood locks up with its neighbor sheets and since you have to be a careful balance beam walker if on the joists themselves. Walking on "doubles", where two joists are connected to each other is easy though since a 6" beam is a lot easier to walk on than a 3" beam.
Another major task of the day was getting the fencing installed. Poles installed immediately after the foundation was poured were trimmed to the right height and capped. Fence pole was strung through the caps for support and then the fence is clamped to the poles. Although not quite finished, the fence is looking great already.
To prevent our lovely new first floor from warping in this rainy time of year, and coat of shallack was applied to the floor. This causes the water to run off without being absorbed into the wood. Our last house had to have two floors reinforced with more plywood because too much warping occurred during rains. So tarps we used were not full proof and water that got under the tarp would be trapped and cause more damage.

Here are some photos of our efforts:

Monday, May 3, 2010

April 17th

Since we were late in kicking off the new house, we decided to have back to back volunteer days in April.
Another great showing from Northrop volunteers helped us put together another successful day.
Work continued removing old concrete from the back yard and leveling it out with extra dirt from the basement. There was still a good deal of old contrete to haul to the dumpster. Also, contractors poured the basement floor and put in the fountation wall in the back of the house where there previously was nothing, so we had to clean out the the house as the contractors left lots of rubble in the basement.



Once the basement was cleaned out, we started framing the basement walls.



We put together a very efficient assembly line and even before lunch we were putting in the 1st floor beams.

After lunch we continued working in the back yard and with framing the basement and putting in beams. By the end of the day we had made some great progress. We were able to finish up most of the first floor, build the opening for the first flood-basement stairs, and get the back yard completely cleaned out and ready for contractors to pour a small patio.

The weather was terrific and everyone had a fun time. Great job everyone on a very successful day!


Tuesday, April 13, 2010

Kick off of our New House

For those of you who followed the progress of our original house at 1606 North Gilmor St, thank you. But, that house is complete and the Smith family are enjoying residing in their new home. Our focus has now shifted to another big project - namely refurbishing 1118 North Fulton Ave. - another three story row home in the Sandtown area of Baltimore.

A lot has happened behind the scenes to get this new house, first Jim Pitts and Ted Imes informed us that Northrop would sponser another house at the dedication. We then sat down with Habitat to decide which house would be a good candidate for us. The city sold the house to Sandtown Habitat, and an architect drew up the refurbish plans for the house. Permits were acquired for the plans, and the Habitat staff gutted the house which was in aweful shape due to lead paint in the house, and just lots of rotting wood.

By the time Kurt, myself and our newest team leader Andrew got there on 4/08/2010 the house looked like this:


There is no roof, no back wall, and nothing but dirt in the basement, not so good. But, with a little love, a lot of hard work, some paint, and before you know it, it will be a home.

We got started on adding the love and the hard work on Saturday April 10th with a large turn out. That was essential because the goal for the day was to dig a pit around the basement to add a drainage ditch. Here we are digging away.



After the 12 inch deep and 12 inch wide ditch was dug, we laid in pipe all around the ditch and filled it with gravel. The pipe has holes in it where water can seep into and if the ground is fully saturated, like after a large rain, the water will run into a sump-pump collection hole and be pumped out. It was a grueling amount of work, but we managed to find time to dig out the concrete pad in the backyard, fill in the big holes in the backyard and mortar up a bunch of joist holes along the walls. Great job everybody!

Here is what the finished product looked like. Habitat and professionals are now in the process of cementing the basement over this gravel and drainage system.


Here is the happy crew, walking back to the warehouse to drop off all the tools we used. (Happy to go home and take a nap after all that shoveling.)